Things change quickly each time a visit is made to the site. Framing on the office area has begun as well as duct work in that area as well. The first layer of exterior material has begun to be hung to the exterior studs. Sorry for the poor quality of the last pictures...had to use my phone. It is projected for the framing to be complete for the entire building by a week from Friday. Hopefully the forecasted rain will not slow things down too much as the framers will be under roof.