The pictures from the 2 posts below were taken today. The post below those 2 were taken Friday. Roofing on the office area is complete and roofing on the worship area began today. As you see, interior studs are up in the education wing as well as door jambs. Also, the tie-in of the main water line to the city water line was being worked on today. Roofing should be complete this week. The crews seem to have been working fast yesterday as much work had been done since Friday.